HI Sudhindra,
For Delivery through project , Material is assigned and wbs,activity should be in release stage.
Please check that also.
Also check reservation that you have created while assigning material.
Normally, for delivery through project process.-reservation through wbs-element work.
Please check these all.
Thanks & Regards
Rahul Bansal